Navigating infrastructure design and authority approvals (IDAS, TPD Approval, ENOC) in Abu Dhabi can be complex and time-consuming—especially when multiple government entities are involved. From transportation planning and utility coordination to securing permits and NOCs, each step demands precision, experience, and a deep understanding of local regulations.
At Super Arc Consultant LLC, we specialize in simplifying this process for developers, contractors, and project managers across the UAE.

How To Obtain TPD Approval?
To obtain TPD (Transport Planning Department) approval in Abu Dhabi (typically under the ITC – Integrated Transport Centre, part of the Department of Municipalities and Transport – DMT), you’ll need to follow a structured process. This is commonly required for developments that impact road networks, access points, or traffic flow.
Here’s a step-by-step overview on how to get TPD approval:
✅ 1. Identify If TPD Approval Is Required
Not all projects require TPD approval. You generally need it for:
- New developments or major refurbishments
- Projects affecting road access or traffic circulation
- Sites requiring parking studies or road modifications
Check with ITC or your consultant if your project qualifies.
✅ 2. Hire a Registered Transportation Consultant
Only ITC-registered transport consultants are authorized to submit and process TPD applications.
They will help prepare:
- Traffic Impact Study (TIS) or Traffic Impact Assessment (TIA)
- Access management plans
- Parking demand/supply analysis
- Road modification drawings if applicable
✅ 3. Prepare & Submit Pre-Approvals and Documentation
Your consultant prepares the initial documentation based on the project scope. Typical documents include:
- Site location and master plan
- Proposed land use and built-up areas
- Existing traffic and road conditions
- Trip generation and distribution estimates
- Preliminary access and parking layout
Submit these through the ITC e-services portal or DMT’s MePS system.
✅ 4. TPD Review and Comments
TPD reviews the submission and may:
- Approve it directly (for small-scale projects)
- Request revisions or clarifications
- Ask for further traffic analysis or simulation
- Request coordination with other departments (e.g., DOT, ADM)
✅ 5. Address Comments and Resubmit
Your infrastructure consultant revises the submission per comments and resubmits. Several iterations may be required until final acceptance.
✅ 6. Obtain Final TPD Approval
Once TPD is satisfied:
- You receive an official approval letter or NOC
- This can be submitted with your building permit application
✅ 7. Post-Approval Compliance
Ensure that all conditions in the approval (e.g., signage, access width, road upgrades) are implemented during construction and verified by authorities at later stages.
Additional Tips:
- Start early. TPD reviews may take 3–8 weeks depending on complexity.
- Engage experienced consultants familiar with Abu Dhabi’s regulations and ITC coordination.
- Use latest ITC/TPD guidelines. These change often; outdated formats may be rejected.